Basic informations - FLAP REPAIR – THE LHOTKA WEIR FOR THE INVESTOR “POVODÍ ODRY, STATE ENTERPRISE

Implementation Date: 10/2016 - 11/2017

Client: QUANTUM, a.s.

Its main part was the exchange of two original weir flaps from the 1960`s that served to regulate the level and flow height. The Lhotka weir on the Odra River, as part of the water management system of the Odra River Basin, provides flood protection for Ostrava, supply of technological water to BorsodChem MCHZ and subscription for a small hydropower plant. As a participant of the “PORR-GASCONTROL” association, we ensured delivery  of project documentation for the realization, production of steel structures of damper weirs, auxiliary and sealing structures, corrosion protection and the assembly of technology.